Erosion during overflowing from water flowing over piles and onto embankment

Basic details

Publish date

02 September 2025

Case ID#

3118

Title

Erosion during overflowing from water flowing over piles and onto embankment

Nation

England

Regulator reference no.

308

Legal status

Statutory

Reservoir type

Non-impounding

Reservoir capacity

10 - 24,999m3

Year of construction

1970 - 1989

Main construction type

Earth fill embankment

Dam height

2 - 4.99 metres

Dam flood category

B

Hazard class

High-risk reservoir

Reservoir use

  • Other

Owner type

Public body

Incident details

Date & Time of incident

25 June 2007 - 12:00

Date incident closed

Observations that caused the incident to be declared

  • Dam or embankment overflowing or overtopping

Describe the incident

In one case, a flood storage reservoir overflowed because its capacity was exceeded. In the other, a river overflowed the defences surrounding it and water flowed into the adjacent flood storage reservoir. In both cases, the embankments had been raised with steel sheet piles. When the water overflowed the sheet piles it dropped vertically onto the earth embankment below causing erosion.

Supporting photos

Causes and impacts

Natural processes which initiated or contributed to the incident

What were the main contributing factors to the incident occurring?

Dam factors

  • None

External factors

  • None

Shortcomings

  • Design shortcoming

What was the root cause of the incident?

Impacts on the reservoir

  • External erosion

Supporting photos

Supporting contributions and studies

Describe any human factors which influenced the incident

Describe any instrumentation at the reservoir and how this was used in warning of the incident or providing monitoring during the incident

There is no instrumentation

Was instrumentation effective leading up to and during the incident?

Not Applicable

Describe any assistance by external parties and impacts on the downstream population

None

Summary of studies or investigations undertaken

The cause of the damage is known and no studies are necessary.

What are the lessons learnt from the incident

Lesson 1

  • Structural
The reservoir was not provided with a dedicated outflow spillway and, had it not been for the need to raise the embankment crest level with sheet piles due to mining subsidence, a well maintained grass embankment may have withstood the flows which have been discharged. The use of sheet piles to raise any embankment which may be subject to overtopping requires very careful detailing and should be avoided, if possible. The emergency reconstruction work involves removal of the sheet piles and raising/re-profiling of the embankment crest with clayey material to an improved profile (1 on 3 side slopes and a 3m wide crest. The crest, a busy public footpath, is to be protected with grasscrete and the grass on the downstream slope is to be strengthened with 'Enkamat' geotextile matting, thus forming a spillway which is designed to withstand any future overtopping events.

Closing comments

Supporting photos