Unpermitted excavation on a flood storage reservoir

Basic details

Publish date

02 September 2025

Case ID#

3263

Title

Unpermitted excavation on a flood storage reservoir

Nation

England

Regulator reference no.

525

Legal status

Statutory

Reservoir type

Impounding

Reservoir capacity

10M+ m3

Year of construction

< 1800

Main construction type

Earth fill embankment

Dam height

2 - 4.99 metres

Dam flood category

A

Hazard class

High-risk reservoir

Reservoir use

  • Flood risk management

Owner type

Public body

Incident details

Date & Time of incident

04 January 2024 - 12:00

Date incident closed

Observations that caused the incident to be declared

  • Other (including pollution and unplanned scour release)

Describe the incident

On two occasions at a large, washland flood storage reservoir, a third party (utilities and highways companies) excavated into a dam crest. A public road runs along the crest. One incident involved installation of a water main under the road. without the knowledge of the undertaker. The other incident involved?constructing a reinforced concrete structure under the public highway. Both occurred without the knowledge of the undertaker. The risk to the dam was that during construction, the integrity of the dam was compromised. The works had temporarily discontinued the site. If a flood event had occurred, increased erosion may have happened at the site. A bigger risk for reservoir safety would be if the contractors did not reinstate the bank to a standard appropriate for a water-retaining structure. In each event, the undertaker became aware of the works and they escalated it within the undertakers organisation. There was no evidence found that the works had a suitable permit or planning permission. The undertaker engaged with the organisations responsible for the works. They ensured that a QCE was consulted on the remaining works and reinstatement of the dam. Investigations are ongoing. The investigation aims to understand how construction works could occur on the crest of the dam without the knowledge of the undertaker. The undertaker aims to find out if there had been involvement of the local planning authority, or the Environment Agency permitting process.

Supporting photos

Causes and impacts

Natural processes which initiated or contributed to the incident

  • Flood - within dam design capability

What were the main contributing factors to the incident occurring?

Dam factors

  • None

External factors

  • Other external factors (describe below)

Shortcomings

  • No apparent shortcoming

What was the root cause of the incident?

Impacts on the reservoir

  • Internal erosion (fill deterioration)

Supporting photos

Supporting contributions and studies

Describe any human factors which influenced the incident

Engagement of the local communities, farmers and other third parties to actively report any issues they observe is encouraged and was the primary source of the issues covered by these two incidents.

Describe any instrumentation at the reservoir and how this was used in warning of the incident or providing monitoring during the incident

There is no instrumentation at the reservoir. It is doubtful whether the incident could have been identified by conventional instrumentation. The Undertakers staff visit the reservoir at regular intervals, there is a local Internal Drainage Board that has pumping assets associated with the reservoir, both within and external to it, who visit those assets regularly and report any issues they see with the dam or Cradge bank.

Was instrumentation effective leading up to and during the incident?

Not Applicable

Describe any assistance by external parties and impacts on the downstream population

On the morning of 4 January, a member of the public reported the incident. The public provided aerial drone imagery.

Summary of studies or investigations undertaken

Seepage is still being monitored and stopped when the water levels in the adjacent river dropped to their normal range. The two breaches were investigated and the cause of the failure identified, for each, as being the result of piping between badger excavations on opposing faces of the cradge bank. Each breach was repaired under the supervision of a QCE when suitable access had been arranged and the reservoir drained of all retained water that entered through the breach.

What are the lessons learnt from the incident

Lesson 1

  • Surveillance and Monitoring
The incident highlights the practical difficulties associated with the surveillance, monitoring and physical intervention of very long internal washlands type cradge banks during high flow conditions

Lesson 2

  • Surveillance and Monitoring
Members of the public can provide valuable assistance in identification and reporting of incidents and the gathering and sharing information of use to the undertaker.

Closing comments

Supporting photos